# Answer key: Ridgeline sample shop (twin-flow 0.4.0-alpha.1)

Sample data, a made-up shop that ships with twin-flow. Every number below was printed by the twin itself (20 runs, seed 0). Your run IDs and folder names will differ. The numbers should not.

## Late orders (twinflow run ... --reps 20 --orders)

| Order | Customer | Part | Qty | Due (end of day) | Typical finish | Late in |
|---|---|---|---|---|---|---|
| WO-26105 | Summit Valve | VB-3107 valve body | 50 | Fri Nov 20 | Fri Nov 20, 6:45 pm | 8 of 20 |
| WO-26107 | Delta Pumps | VB-3107 valve body | 30 | Mon Nov 23 | Tue Nov 24, 11:30 am | 16 of 20 |
| WO-26110 | Summit Valve | VB-3107 valve body | 45 | Wed Nov 25 | Mon Nov 30, 5:58 pm | 20 of 20 |
| WO-26112 | Delta Pumps | VB-3107 valve body | 35 | Tue Dec 1 | Wed Dec 2, 11:42 am | 16 of 20 |
| WO-26115 | Summit Valve | VB-3107 valve body | 40 | Fri Dec 4 | Fri Dec 4, 1:44 pm | 1 of 20 |

The other 10 orders (all fittings and brackets, plus WO-26102) are on time in all 20 runs.
The "on-time 12 (80%)" line at the top of the run is the first run only.

## Bottleneck

Busiest work centers: mill_VB 93%, mill_MB 31%, lathe_FTG 22% (busy share of on-shift time).
The valve-body mill takes 45 minutes a piece (rate 0.0003704 pieces a second) and 45 minutes of setup a job (load 2700 seconds).

## Today and two fixes (twinflow balance ... --reps 20)

| Test | On-time over 20 runs | Late orders per run |
|---|---|---|
| Today (scenarios/today.json) | 79.7% | 3.05 |
| Second valve-body mill (my-tests/second-mill.json) | 95.7% | 0.65 |
| Saturday shift for the machinists, 6 am to 10 pm (scenarios/saturday-shift.json, point-0001) | 93.7% | 0.95 |

Late orders per run come from summary.json in each balance folder.
The twin does not count what a mill costs or what Saturday pay costs. It does not pick a winner.